PTS Bond 2017
Phoenix High Summary
Project
New school and renovations to existing building
- Prioritize CTE spaces (seven CTE programs: business, construction, agricultural science, welding, media arts, culinary and auto)
- New athletics stadium (turf field, stadium bleachers, concrete seating area)
- Four new tennis courts
- Increase safety and security
- New theater
Project Description
Construct new high school – 100,000 square feet
Renovations to existing building – 56,000 square feet
SCHEDULE AND MILESTONES | START | COMPLETION |
---|---|---|
Bid and award site package | May 1, 2019 | June 1, 2019 |
Bid and award building package | August 1, 2019 | September 5, 2020 |
Construction | June 17, 2019 | December 13, 2020 |
Owner occupancy | December 15, 2019 | January 6, 2021 |
Post occupancy evaluation | January 1, 2020 | January 6, 2021 |
Warranty period | January 1, 2020 | January 1, 2021 |
Construction (renovation phase) | December 29, 2020 | October 1, 2021 |
Owner occupancy (renovated space) | January 1, 2020 | December 1, 2021 |